Chedoke Creek Remediation
Chedoke Creek updates provided to Hamilton City Council and Standing Committees.
Chedoke Creek Remediation Workplan
The City of Hamilton was served a Ministry of the Environment, Conservation and Parks (MECP) Order on December 4, 2020, as a result of the Main/King Combined Sewer Overflow discharge that occurred between January 2014 and July 2018. The City of Hamilton has been working closely with the MECP and the Royal Botanical Gardens (RBG) to develop a remediation workplan for both Chedoke Creek and Cootes Paradise in response to the Order.
Chedoke Creek Targeted Dredging
The goal of the targeted dredge project is to improve the condition of the creek prior to the beginning of the discharge event. As indicated in the MECP approved Chedoke Creek Workplan, the City implemented short term offsetting remediation projects in areas around lower Chedoke Creek and Princess Point to further improve the condition of the water. The Cootes Paradise Workplan addresses the long term offsetting work required by the order. The goal of the Cootes Paradise Workplan is to improve the quality of water into both Chedoke Creek and the receiving bodies of water.
Project Update:
On December 20, 2022, the MECP Director approved the City’s requested deadline extension to December 31, 2023, with all other items in the Order remaining in effect, and unaltered. On March 3, 2023, the MECP Director issued a revised amendment which requires that the in-water targeted dredging work be completed by August 31, 2023, with the remaining activities in the approved Chedoke Creek Workplan completed by December 31, 2023.
Subsequently on March 14, 2023, after positive and collaborative discussions between the City and the MECP, the MECP Director issued a revised amendment, which supports the City’s concerns regarding the previous deadline and still expedites the remediation of Chedoke Creek. As such, the City is now required to complete the in-water targeted dredging work on or before October 31, 2023. On October 13, 2023, due to the unseasonably wet weather experienced through July and August, as well as equipment challenges caused by larger rocks and unexpected materials within the dredged footprint, the City of Hamilton requested a 1-month extension moving the in-water work deadline from October 31, 2023, to November 30, 2023. On October 30, 2023, the MECP granted the extension requiring the City of Hamilton to complete all dredging activities by November 30, 2023, and complete the remaining activities in the approved Chedoke Creek Workplan by December 31, 2023.
On November 17, 2023, the project team successfully completed the targeted dredging activities, concluding the four-month effort to remove sediment from the bottom of Chedoke Creek.
The transportation of the dried sediment off the Kay Drage Park site subsequently began on December 1, 2023. As required by the Order, all of the approximately 16,000 tonnes of sediment was disposed by December 31, 2023. Approximately 300 truckloads was needed to transport all the sediment to approved landfills
Offsetting projects, removal of sediment (targeted dredging) and potential impacts to the community
Frequently Asked Questions
The City of Hamilton has taken all necessary steps to ensure wildlife and species at risk located within Chedoke Creek and Cootes Paradise are protected throughout the remediation process. These steps have been in accordance with all six governing bodies including the MECP, Hamilton Conservation Authority, Ministry of Transportation, Transport Canada, Fisheries and Oceans Canada and Royal Botanical Gardens to proceed with remediation work. Some of the measures taken include:
Pre-dredge/during dredge:
- Before moving ahead with targeted dredging, Species at Risk (SAR) investigations were required by Fisheries and Oceans Canada and the Ministry of Conservation and Parks to be completed by the City of Hamilton in 2021. The investigation concluded that the Lilliput mussel was the only SAR identified that has the potential to be within the project area.
- In June 2022, Lilliput mussels were collected and relocated by two qualified aquatic biologists hired by the City.
- In August 2022, The City of Hamilton completed bluegill habitat enhancement work in Cootes Paradise as part of its Ministry of Environment, Conservation and Parks (MECP) permit. By installing over 10 brush piles, 35 nesting structures and five root wads, the City is improving bluegill habitats, and by extension, Lilliput mussels that latch on to bluegill fish.
- Based on the Ministry of Northern Development, Mines, Natural Resources and Forestry regulations and the fish species present, in-water work is prohibited from March 15 to July 15 each year to ensure no negative impacts on fish spawning.
- Prior to dredging activities, each work area in the creek is isolated using a turbidity/silt curtain that includes a weighted line to maintain bottom contact, and a floating line to isolate the work area at the surface. Fish and wildlife are excluded from the work area prior to the dredging activities by a qualified aquatic biologist, mitigating potential interaction with the dredging operation in accordance with governing protocols.
Post-dredge:
- Various post-dredging monitoring efforts will take place to support each agency’s permitting and approval requirements including monitoring any changes in water levels, sediment quality of the newly exposed creek bottom and the functionality of any added species at risk habitat.
The dredging will occur in two separate dredge zones – north and south. Work will start at the north end of Chedoke Creek, near the Desjardin pedestrian bridge and will move southwards toward Kay Drage Park. Residents will be able to see the dredge machine from the waterfront trail and Desjardin pedestrian bridge while work occurs in the north zone.
Residents can still expect to see some work occurring in wet weather conditions.
Permitting requires that the creek flow remain unimpeded, so each dredge zone will be broken down into smaller isolated sections covering only ½ the creek.
Turbidity curtains separate the work zone and allow the creek to continue flowing, while also allowing the City to safely isolate from any wildlife and keep the dredge material from disrupting the rest of the creek.
The Chedoke Creek Workplan outlines the steps associated with targeted dredging in Chedoke Creek. This work will remove nutrient laden sediment from the creek bottom and is scheduled to be completed before the end of 2023. The goal of the targeted dredge project is to improve the condition of the creek prior to the beginning of the discharge event.
The Cootes Paradise Workplan addresses the long-term offsetting work required by the order. The goal of the Cootes Paradise Workplan is to improve the quality of water into both Chedoke Creek and the receiving bodies of water.
Once the sediment is removed from the creek using the hydraulic dredge, it will be transported via pipeline to the dredge material management area which is located within Kay Drage Park. In order to remove and dispose of the sediment efficiently, dewatering will occur at the dredge material management area. A lined trench will be built within the material management area to facilitate the dewatering process. The sediment slurry (mix of solid material and water) will be pumped into a geotextile container. An environmentally safe polymer is added to help bind the solids together and separate the water. The separated water will then drain from the geotextile container while the sediment remains inside. The separated water will be pumped to a nearby sanitary sewer main (on dry days only) to be treated at the Woodward Wastewater Treatment Plant. Once the container is full of sediment and the contents have dried, it will be hauled to a landfill.
Sediment remaining in the Geotubes are anticipated to be disposed of offsite at a non‐ hazardous waste disposal facility. The disposal timeline will depend on the dredging completion date and the dewatering rate of the sediments. The contractor will monitor the dewatered sediment prior to disposal to ensure the material is fully dewatered, dry and passes a slump test to be classified as solid non‐ hazardous waste.
Dredging will be completed hydraulically. This means we will be vacuuming up the sediments (or solids) from the bottom of the creek. The hydraulic dredge utilizes a cutterhead and pump to vacuum and transport the sediments to the dredge material management area via pipeline. The average combined dredge depth will be approximately 1.0 m which will remove approximately 8,000 m3 of sediment from the bottom of the creek.
No – the site will look as it did before work started. Kay Drage Park is expected to be restored to its original condition and re-open to the public at project completion.