Lane Restrictions and Road Closures
For questions about road closures
Call 905-546-2489 (CITY)
Subscribe to Road Closure e-Updates
Subscribe to scheduled closure information for City of Hamilton roadways. The number of notifications sent to subscribers is unpredictable.
Lane Restrictions & Road Closures
An interactive map that displays lane restrictions and road closures for construction, occupancy permits and special events. View map in separate window
Listing of scheduled lane restrictions and road closures
The listing does not include unscheduled or emergency closures.
| Start Date | End Date | Road Closure Limits | Reason for Closure |
|---|---|---|---|
December 3 at 8am | December 3 at 4pm | Temporary road closure | Crane works |
November 29 at 6pm | November 29 at 10pm | Temporary road closure | Flamborough Santa Claus Parade |
November 28 at 3pm | November 28 at 11pm | Temporary road closure | Dundas Holiday Tree Lighting event |
November 27 at 6am | November 27 at 11pm | Temporary road closure | Crane works |
November 26, 2025 | January 14, 2026 | Temporary road/intersection closure | Construction |
November 26, 2025 | December 19, 2025 | Temporary lane closures | Construction |
November 25, 2025 | November 26, 2025 | Temporary lane occupancy | Watermain connections |
November 25 at 9am | November 25 at 5pm | Temporary road closure | Watermain connections |
November 24, 2025 | November 25, 2025 | Temporary road closure | Construction |
November 24 at 9am | November 24 at 5pm | Temporary road closure | Sewer connections |
November 24 at 9am | November 24 at 3pm | Temporary lane occupancy | Water service installation |
November 21, 2025 | November 30, 2025 | Temporary road closure | Hess Winter Village event |
November 21 at 9am | November 21 at 3pm | Temporary lane occupancy | Scaffolding removal |
November 19 at 9am | November 21 at 5pm | Temporary road closure *Rescheduled | Sewer repairs & asphalt paving |
November 19 at 6am | November 26 at 6pm | Temporary road closure *Extended | Planned CN full crossing rehabilitation |
November 17, 2025 | December 5, 2025 | Temporary road closure | Roadway repairs |
November 17, 2025 | November 21, 2025 | Temporary lane occupancies | Sewer system testing |
November 10, 2025 | November 21, 2025 | Temporary road closure | Ditching work |
October 22, 2025 | Approx. 5 weeks | Temporary lane occupancy | Asphalt & repaving |
October 14, 2025 | December 19, 2025 | Temporary lane occupancy | Sewer and watermain infrastructure installation |
October 14, 2025 | November 25, 2025 | Temporary road closure | Underground Hydro works |
September 29, 2025 | September 2026 | Temporary lane closures This work is part of a larger infrastructure renewal project. PSA: Safety reminder for Dundas St. Commuters during Grindstone Bridge construction | Bridge replacement |
September 15, 2025 | November 21, 2025 | Temporary lane occupancies | Roadway widening activities |
September 14, 2025 | Extended closure, TBD | Long-term road closure | Environmental Assessment |
September 8, 2025 | Approx. 8 to 9 weeks | Temporary lane occupancies | Asphalt & concrete work |
September 1, 2025 | November 30, 2025 | Temporary road closure | Roundabout construction (MTO Project) |
June 18, 2025 | November 27, 2025 | Temporary road closure *Extended | MTO roundabout construction |
June 9, 2025 | Late December 2025 | Temporary road closure | Bridge replacement |
March 24, 2025 | Until further notice | Temporary road closure | Sanitary sewer and watermain construction |
March 17, 2025 | December 2025 | Temporary full & partial road closures: PSA: Construction on Wilson St & Sherman Ave begins March 17 | Road reconstruction |
June 28, 2024 | December 2025 | Lane closures | First Ontario Centre renovations |
October 30, 2023 | September 2026 | Dickenson Road at the Trinity Church Rd intersection | Tunneling construction |